GENERAL TERMS AND CONDITIONS OF SERVICE
(Continued)
18. OPERATIONAL FLOW ORDERS ("OFO") (Continued)
18.3 (Continued)
NBP will post information about the status of operational
variables that will determine when an OFO will begin and end. NBP
will post a notice on its website informing Shipper(s) when any
OFO in effect will be canceled. Following the issuance of an OFO,
NBP will post information on the factors that caused the OFO to be
issued and then lifted as soon as it is available.
18.4 Except in cases where the curtailment of interruptible services
would not alleviate the causes or conditions necessitating the
issuance of an OFO, NBP will, where practicable, curtail
interruptible services prior to issuing an OFO. NBP shall not be
required to curtail interruptible services to individual Shippers
when curtailment of service to those Shippers would not affect the
OFO.
18.5 Upon the issuance of an OFO by NBP, it shall be incumbent upon
Shipper to adjust Gas supplies as directed within the time frame
specified in the OFO. Failure to comply in a timely fashion with
an OFO may result in an immediate interruption of all or a portion
of Shipper's service and cause Shipper to incur a penalty of $25
per Dth plus the Spot Index Price (equal to the SoCal Gas large
packages price as reported in Gas Daily's Daily Price Survey) per
Dth for all quantities in excess of that allowed under the OFO.
The payment of unauthorized overrun penalties does not create the
right to exceed the levels established by an OFO.
(Continued)
|
Issued by: John A Roscher, Director of Rates & Reguatory Affairs
Issued on: September 9, 2002 Effective on: August 12, 2002
Filed to comply with order of the Federal Energy Regulatory Commission, Docket
No. RP02-363-000, issued August 9, 2002 |